Construction work: connexion to district heating

The current oil-fired heating system, installed in the 1950s, is obsolete and could break down at any time. Its replacement is essential and must be carried out as soon as possible. The new installation will be environmentally friendly and economical, but will require major work.

The work will be carried out in several stages:

  • From 24 April until the end of June 2023, excavation work will be carried out in the garden. Access through the gate will be closed, as will the entire garden on the station and railway side. Pedestrian access will be via the main staircase and the rear gate. Wheelchair access will be possible, but you will need to register at the candle counter to be accompanied.
  • In the second stage, technical installations will be carried out in the basement. Information regarding dates and access will be communicated in advance.